Acceleration Claims

Belmont has extensive experience evaluating and preparing acceleration-related claims for our clients. The old saying that “Time is money” is especially true on construction projects. Typically, construction contracts clearly spell out key milestone dates, completion dates, and possibly liquidated damages for delay or early completion bonuses. Thus, time plays an important factor in project decisions.

Agreed-upon project schedules allow the owner the opportunity to efficiently plan its production operations and therefore generate revenue, while the contractor can efficiently plan its use of labor, equipment, and resources to optimize the construction process. Acceleration occurs when a contractor’s work is expedited to complete a particular work activity earlier than planned. A contractor may accelerate voluntarily in order finish the project earlier to move on to its next job, to mitigate its own delays and inefficiencies, or to save money by reducing the project duration, in which case an acceleration claim is unlikely. Additionally, the contractor may decide to accelerate the work in an attempt to complete the project earlier than scheduled to meet project completion bonuses for early completion. Typically, these voluntary decisions by the contractor to accelerate do not result in acceleration claims, as it was the contractor’s decision to accelerate the work.

Acceleration claims are typically encountered on construction projects when the contractor makes efforts to recover the project schedule after the project has suffered delays due to causes it believes are beyond its control. There are several ways in which the work can be accelerated, including, but not limited to working overtime or implementing a new shift, providing additional labor, adding other resources (i.e., equipment), and re-sequencing work activities. Each of these acceleration efforts can be effective in some cases; however, acceleration efforts can be expensive and do not guarantee early or on-time completion of the work. Adding resources, such as labor and equipment carries extra costs. Working overtime hours typically requires paying premium labor rates of 1.5 to 2 times base labor rates to provide incentive to work the additional time.

There are two primary types of acceleration on construction projects that are subject to construction claims: directed acceleration and constructive acceleration. Situations in which the owner directs the contractor to accelerate the work are typically referred to as directed acceleration or, more simply, acceleration. Directed acceleration occurs when the owner directs the contractor to accelerate to complete the project in advance of the planned or specified completion date.

As stated, time is money and accelerating a construction project also costs money. In addition to the direct cost of the work, acceleration also may result in an overall loss of labor productivity. It is recognized in the construction industry that acceleration efforts such as working overtime and shift work, performing out-of-sequence work, stacking trades, and overcrowding on the project site contribute to reduced labor productivity. In addition, when a contractor adds labor, there may be a loss of labor productivity as new workers may not be familiar with the work or may require training before achieving normal levels of productivity. It is interesting to note that a contractor typically does not have to prove that the acceleration effort was successful at improving the schedule. It is normally necessary to show that it reasonably attempted to accelerate the work and that the acceleration efforts resulted in additional costs.

© 2011 Belmont Construction Corporation. All Rights Reserved